Gattendorf, Austria – Wind farm Gattendorf Nord II – Construction monitoring

  • CES HOME
  • 5
  • PROJECTS
  • 5
  • Gattendorf, Austria – Wind farm Gattendorf Nord II – Construction monitoring

For the wind farm Gattendorf Nord II, GE as general contractor is erecting 4 wind turbines of the 5 MW class. The turbines will be deep-founded using SOB piles. Owner and operator of the wind farm is the Püspök Group.

OUr services

CES has been contracted by GE for the construction supervision and the execution supervision of the deep foundations as well as the foundation construction works. Furthermore, CES provides the Environmental Health and Safety (EHS) coordinator.

Location:

Central Europe,
Austria

Duration:

2021-03 -
2022-10